Client: |
|
|
Contact: |
mmi.com.sg |
|
Type of Business: |
HDD (VCM) |
|
Project Title: |
MMI C/R 1 (Class 100, 1K) |
|
Location: |
Navanakorn Industrial Estate, Nakorn Ratchasima, Thailand. |
|
Dates: |
Feb 2011-Jul 2011 (Phase 2) Jan 2012 – Mar 2012 (Flood recovery) Jul 2018 – Oct 2018 (Expansion) (Original Phase 1 Contract done by QDot in 2005) |
|
Scope of services: |
Detailed Engineering Design, Construction Management, Procurement Management, Commissioning and Validation. |
|
Area Size: |
2,500 sqm (Phase 2) |
|
Project Profile: |
Project Highlights
- Cleanroom area 2,500 sq.m
- ISO#5 (Class 100)
- ISO#6 (Class 1000)
- Raised floor, Ceiling grid with FCU in ceiling plenum chamber
- BMS
- Electrical works (Power, Lighting, Fire alarm, Security & access control, CCTV, Lightning & grounding, etc.)
- NFPA standard compliance
- NEBB